Excavation and groundwork operations begin at the Indrabhavan Apartment site, preparing the foundations for construction.
On the eighth floor at Kalpvishwa, the primary deck beam framework is complete and metal decking is now being laid — the floor system is advancing toward reinforcement placement and concrete casting.
Shivatman has entered its final phase: construction and finishing works are substantially complete, and attention has turned to the façade, campus, and finishing details as the building moves toward handover.
At New Castle in Baner, the superstructure has risen above the lower levels and the building's architectural language is beginning to emerge through its defining ledges, proportions, and external form.
At the Forest Rest House, the masonry walls of the 2BHK are complete and formwork for the concrete roof band is now up — the building has moved from foundation to enclosure and is preparing for the roof above.
Work has begun on site at Dandekar Bridge, where the first phase of the mixed-use neighbourhood is taking shape from the ground up.